Project Schedule

Initial site preparation activities will commence in mid August 2002 with project completion scheduled for late September 2004. Installation of temporary site electrics, piling and earth works will commence in late August 2002 and be completed in March 2003. Civil work will commence in late October 2002 and is followed by structural steel erection commencing in early March 2003.

Installation of mechanical and electrical equipment, piping and electrical bulk commodities will commence in late January 2002. Pre-commissioning and Startup (commissioning) activities will commence in early June 2003, continuing until their completion in late September 2004.